Project: completion gate (FGS ABBI.364) | user abbiadmin | realm v200c | objective session 65192e75
State as of the coordinator hand-over, last entry 2026-11-14 00:03Z. Source: coordinator task list for tasks; objectives ledger for deliverable status. Task states not recorded there are shown as unknown, not inferred. Elapsed times are measured to 00:03Z.
| Deliverable | Task | Execution type | Dependencies | Model / agent | Elapsed | Estimated finish |
|---|---|---|---|---|---|---|
| Deliverable status (objectives ledger): D1, D2, D3, D4, D5 and D7 COMPLETE. D6 OPEN. | ||||||
| D1 | Completion-gate service on M7, safe for many sessions at once - COMPLETE | |||||
| D2 | Sessions on several machines get correct verdicts from the service at the same time - COMPLETE | |||||
| D3 | The missing-ledger trap closed, reproduced first - COMPLETE | |||||
| D4 | Checks proven able to fail, one known-bad case per check - COMPLETE | |||||
| D5 | Test evidence no longer depends on the broken test harness - COMPLETE | |||||
| D6 | The gate made non-optional on measured evidence - OPEN. Enforcement half is NOT switched on (project manager decision under the Architect's delegated authority): the engine observes and the producer warns. | |||||
| D7 | One authoritative engine, and the prior objective formally closed - COMPLETE | |||||
| D6 | Producer r4 (warn mode) | Done (landed) | None open | Agent not recorded | Landed 20:47:36Z (about 3h16m before 00:03Z) | Landed. First real warn line not yet seen; waiting on the next real close. No date. |
| D6 | Combined engine swap and signer restart (M7) | Dependent | Signer five-fixes verify; combined-rollback rehearsal on M6; 24 clean watch hours; project manager GO live in the 2-minute post-cycle slot | Executing model not recorded | Not started (planned) | Planned Sat 2026-11-14 14:00Z |
| D6 | Combined-rollback rehearsal on M6 | Concurrent with signer verify | Signer integration (done) | Rehearsal agent, model not recorded | Started 23:13:31Z (about 0h50m). Core stage passed 00:01Z (20 of 20 checks). Launchd restart-form measurement blocked over ssh, so not measured; default stays bootout plus bootstrap | Must finish before 06:00Z Sat (M6 window end). Otherwise the 14:00Z slot cannot run. Unknown whether it will finish |
| D6 | Signer five-fixes track (plus fix 6) | Concurrent with rehearsal | Integration runs (done, 16 runs); r3c queue held | Verify agent, model not recorded | Verify started 23:13:31Z (about 0h50m) | Independent verify in progress. Finish unknown |
| D6 | Watch r2d (fix and verify) | Concurrent | Re-verify before install; installs after the trial ends | Workflow agent, model not recorded | Resumed 23:50Z (about 0h13m this run) | Unknown |
| D6 | Copy-B catch-up (4 files plus 2 adopt rows) | Concurrent with the committer build, under 4 project manager conditions | Condition 1 (offline acceptance proof), 2 (versioned way back), 3 (canary), 4 (lane-rule hash). Nothing filed or deployed yet | Plan agent, model not recorded | In planning. Relaunched 23:50Z (about 0h13m) | Unknown |
| D6 | D2 concurrent re-proof harness | Dependent | Engine swap plus 2 clean cycles; project manager line before live fire | Offline build done by workflow agent, model not recorded | Harness CONFIRMED (34 of 34 offline controls, 25 of 25 mutants) | Live fire after the swap (after Sat 14:00Z). Not scheduled |
| D6 | Enforcing rule set design (M7-side evidence only) | Dependent | Engine live; enforcement stays off until the panel clears it | Model not recorded | Not started | To the panel about Mon 2026-11-16 18:00Z |
| D6 | Forwarder exception and direct client | Dependent | Engine live. Direct client needs 3 M7-side controls (op filter, field whitelist, root-only audit log) | Model not recorded | Not started | Exception dated Nov 19; direct client after the engine is live |
Site status: first published 2026-11-14 after the Change Gate filings for this site were accepted. Deliverable status is from the objectives ledger; task rows are from the coordinator hand-over at 00:03Z.